So I have four of my 4.5" Plano Convex 1920's fixtures lighting my work home shop as re-lamped and bench focused for 35w/12v MR-16 lamp. I run them off a wire rope type track lighting 12v. transformer rated at 15A in center circuit breaker. Only four of the fixtures no more than 25' away from the transformer. 14ga wire feeding the individual fixture feeders and 14 to 16ga. wire feeding the transformer.
Load side breaker was 15A and one would think as opposed to wire rope feeding the fixtures, I’m now copper in direct, it should be sufficient to power up four 35w fixtures. Not persay in question of the breakers in going thru many of them, more just a question of wire gauge or non-sufficient breaker somewhere? Where did I go wrong in this system working last year but now problematic this year after changing breakers?
14ga cable at up to 25' given 35w/12v lamps as split into four fixtures, or more about the transformer or power supply to it from switch which is 16 ga. at about ten foot in 16/7 multi-cable? Why are these load side thermal breakers overheating a year or more after the install given the above assuming the load side breaker is doing its job at 15A for blowing in output for the 12v/35A load side?
Feeder to this and another circuit is 16/7 multi-cable. Goes up from the switch for the low voltage switched circuit and line voltage dimmer circuit up a few feet to a patch box for total length of 16/7 cable to about 10'. From there it is 14/3 to the tranformer in feeding it about five feet away.
Feeder wire to the transformer too small or transformer too small in being huge? Thought against many lines but yet to solve the problem. Mostly I think it adds up in should work... where did I calculate wrong?
Load side breaker was 15A and one would think as opposed to wire rope feeding the fixtures, I’m now copper in direct, it should be sufficient to power up four 35w fixtures. Not persay in question of the breakers in going thru many of them, more just a question of wire gauge or non-sufficient breaker somewhere? Where did I go wrong in this system working last year but now problematic this year after changing breakers?
14ga cable at up to 25' given 35w/12v lamps as split into four fixtures, or more about the transformer or power supply to it from switch which is 16 ga. at about ten foot in 16/7 multi-cable? Why are these load side thermal breakers overheating a year or more after the install given the above assuming the load side breaker is doing its job at 15A for blowing in output for the 12v/35A load side?
Feeder to this and another circuit is 16/7 multi-cable. Goes up from the switch for the low voltage switched circuit and line voltage dimmer circuit up a few feet to a patch box for total length of 16/7 cable to about 10'. From there it is 14/3 to the tranformer in feeding it about five feet away.
Feeder wire to the transformer too small or transformer too small in being huge? Thought against many lines but yet to solve the problem. Mostly I think it adds up in should work... where did I calculate wrong?
Last edited: